Everything’s Bigger in Texas, Including the Construction Litigation (Part 3 of 3)

Image by skeeze via pixabay.com

Image by skeeze via pixabay.com

This is the third of a three-part series exploring the Texas Supreme Court’s decision in Zachry Construction Corp. v. Port of Houston Authority of Harris County.  A summary of the case can be found at Part 1 of the series.  Part 2 addressed the “no-damages-for-delay” aspects of the case and commented upon the current state of North Carolina jurisprudence on the enforcement of such contract clauses.  This post explores the decision’s holding with respect to lien waivers and highlights some key issues contractors should bear in mind before executing these often-overlooked instruments.  

What Zachry Says About Lien Waivers

By way of reminder, here’s the pertinent lien waiver language that gave rise to the dispute over whether Zachry waived its right to claim $2.36 million in liquidated damages (“LDs”) that had been withheld by the Port Authority:

[Zachry] hereby acknowledges and certifies that [the Port Authority] has made partial payment to [Zachry] on all sums owing on Payment Estimate Number [–––] and that it has no further claims against [the Port Authority] for the portion of the Work completed and listed on the Schedule of Costs in Payment Estimate Number [–––].

The Port Authority argued this language constituted a waiver of all claims for payment; Zachry argued it only applied to lien claims.  The trial court saw it Zachry’s way, and the Texas Court of Appeals reversed.

The Texas Supreme Court thought the jury got it right.

Continue reading →

Leave a comment

Filed under Case law from other states, Lien Law

Everything’s Bigger in Texas, Including the Construction Litigation (Part 1 of 3)

Because my practice is focused almost exclusively on construction projects in North Carolina, I focus far more attention on local case law developments than on appellate decisions from other states.  But every now and again, a decision from some far-flung jurisdiction gets published that is just too big, too fascinating and too important to overlook.

Zachry Construction Corp. v. Port of Houston Authority of Harris County, handed down by the Supreme Court of Texas (the “Texas Supreme Court”) on August 29, 2014, is just such a decision.

Continue reading →

2 Comments

Filed under Case law from other states, Delay Claims, No Damages for Delay Clauses