Legislative Committee Set to Vote on Recommendations for Strengthening Liens on Leaseholds in North Carolina

Embed from Getty Images
UPDATE 4/8/2014 9:45 a.m.: The Committee voted yesterday, April 7, 2014, to embrace only the second of the three recommendations discussed in my original blog post below.  I have struck through the recommendations that did not survive the final draft of the report, which is now in the hands of the Legislative Research Commission for further action.  Many thanks to Raleigh construction attorneys Jason Herndon and Brian Schoolman for alerting me to the Committee’s vote, as a trip out-of-state prevented my attendance at yesterday’s meeting.

The Legislative Research Committee charged with studying the lien rights of contractors and materialmen on tenant improvement projects meets a week from today, on April 7, 2014, to vote on a series of recommendations to the 2014 Session of the North Carolina General Assembly.  The Committee’s recommendations can be found in its recently released draft report.

Continue reading

Leave a comment

Filed under Lien Law, State law, policy & news

Crazy S#!% in Construction Contracts

Embed from Getty Images

It’s springtime in the construction industry, my friends.  Banks are lending again, optimism has returned and the private, non-residential sector is heating up.  Good news all.

But before you mobilize the yellow steel to your next jobsite, the deal’s gotta get done.  And so ’tis the season of contract negotiation — which, if you’re not careful, could lead to the season of your discontent.  That’s because some crazy stuff might be lurking in the document the party above you in the contractual chain wants you to sign.

Just ask Birmingham, Alabama construction attorney Burns Logan, the inspiration behind this post and its cheeky title:

https://twitter.com/BurnsLogan/status/448940036642570242

There’s only one way to suss out the crazy in your construction contracts, and that’s by carefully reviewing them, as Sage Construction reminded us this week:

https://twitter.com/SageConstruct/status/449212751068405760

One of the three reasons cited in the linked blog post is “owners are pushing risk to GC’s.”

Tell me about it!

Continue reading

2 Comments

Filed under Contract Review & Negotiation

Your Date of Last Furnishing of Labor Might Be Earlier Than You Think

Embed from Getty Images

Meeting lien and bond claim filing deadlines can sometimes feel like a race against the clock.  For claimants who provide on-site labor for a construction project, properly identifying the date such labor was last furnished is a critical component to winning that race.

Wednesday WisdomAn unpublished Fourth Circuit Court of Appeals decision illustrates the point.  In U.S. ex rel. Mavis Mechanical Services, Inc. v. Hanover Ins. Co., 182 F.3d 910 (4th Cir. 1999), a subcontractor on a federal construction project tried to establish compliance with the Miller Act’s one-year filing deadline by arguing it furnished labor on two occasions within a year of its lawsuit.  The first instance involved attendance at a coordination meeting; the second involved mobilization to the site to perform certain valve installation work it had yet to complete, but refusal by the sub to actually perform the work when the GC refused to make payment on alleged past due amounts.  On these facts, the Fourth Circuit upheld the district court’s determination that neither site visit qualified as “labor” for the purposes of the Miller Act’s one-year filing deadline.  That holding doomed the sub’s Miller Act claim to dismissal.

The moral of the story?

Continue reading

Leave a comment

Filed under Lien Law, Payment Bonds

Five Key Points to Understand About OSHA’s Proposed Airborne Silica Standard

Embed from Getty Images

The Monday Memo in recent weeks has focused on North Carolina laws and policies bearing on the Tar Heel State’s construction industry.  Today I turn my gaze to our nation’s capitol, where public hearings are underway on OSHA’s proposed rule to lower the permissible exposure limit (“PEL”) for airborne crystalline silica, a by-product of such common construction operations as concrete and stone cutting.

Monday MemoThe hearings began on Tuesday, March 18 and continue through Friday, April 4, with a variety of construction industry and safety voices scheduled to be heard.

Here are five key points to bear in mind as the process moves forward:

Continue reading

Leave a comment

Filed under Federal law, policy & news, OSHA

Don’t Blame Me When It’s All Your Fault: the Role of Anti-Indemnity Statutes in Construction

Embed from Getty Images

Nobody likes being blamed for somebody else’s mistake.  Worse still is shouldering the financial burden on account of another’s wrongdoing.

Yet that’s precisely the position many contractors and subs find themselves in as the result of the presence of an indemnity clauses in their construction contracts.

To my way of thinking, it is fundamentally unfair to shift the entire risk of one’s own negligence to another party.  As my Twitter feed has revealed over the last week or so, the state legislatures in Missouri and Minnesota are in the process of wrestling with that unfairness:

The good news for North Carolina contractors is that the Tar Heel State has a statute on the books preventing one party from shifting the entire risk of its own negligence to another.

Continue reading

1 Comment

Filed under Indemnity Claims, State law, policy & news

Prefer to Serve Your Own Lien & Bond Preliminary Notices? These Three Web Tools Can Help.

Wednesday WisdomWhile the conservative approach is to rely on an experienced construction attorney to serve preliminary lien and bond notices for North Carolina construction projects, there are many subs and suppliers who prefer the DIY approach.  I’m sure many of you do-it-yourselfers already rely on these web-based tools for facilitating your preliminary notices, but just in case, here are my three favorites:

Continue reading

1 Comment

Filed under Lien Law, Payment Bonds, State law, policy & news, Subcontractors, Technology

North Carolina Will Now Revise Its Building Code Every Six Years, Instead of Every Three

Monday MemoPrepare to hold onto your 2012 North Carolina Building Code until 2019.

On March 11, 2014, the N.C. Building Code Council voted to update the commercial building code once every six years, instead of once every three years under current regulations.  The six-year commercial code cycle now mirrors the update schedule for the residential code, which was changed to a six-year cycle by House Bill 120, signed into law by Governor McCrory on June 19, 2013.

As an exception to the new six-year rule for commercial buildings, the electrical code will continue to be updated on a three-year cycle.

The Council’s vote to place the commercial code update on a parallel track with the residential code’s six-year cycle was close: 9-6.  Why such a sharp split?

Continue reading

1 Comment

Filed under Building Codes, Local law, policy & news, State law, policy & news

Bidder Prequalification & Fairness in Public Contracting

Friday ForumWith last year’s passage of House Bill 857 in the North Carolina General Assembly, public contracting agencies in the Tar Heel State have no shortage of project delivery methods from which to choose.  From design-bid-build to construction management at-risk, design-build, design-build bridging and P3s, our state statutes now authorize a veritable cornucopia of options for procuring public construction contracts.

But the following tweet from ENR’s Tom Sawyer earlier this week got me wondering: is the state overlooking another viable procurement option?

Continue reading

2 Comments

Filed under Project Delivery Systems, Public Bidding, State law, policy & news

A Trap for 2nd-Tier Miller Act Claimants to Avoid

Wednesday WisdomMost second-tier Miller Act subs and suppliers understand that in order to recover under a prime contractor’s Miller Act payment bond, written notice of the claim must be made to the contractor “within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made.”  40 U.S.C.A. § 3133(b)(2).  With that 90-day rule in mind, consider the following hypothetical:

You’re a second-tier supplier who last furnished materials to a first-tier subcontractor on a Fort Bragg project on December 13, 2013.  Today is the 89th day since your last furnishing, and you still haven’t been paid.  Realizing your claim notice deadline is fast approaching, you send your claim to the prime contractor by certified mail, return receipt requested this morning.  The prime will receive the notice and sign the green card on March 14, the 91st day after your last furnishing.  Was your notice of claim timely?

Continue reading

3 Comments

Filed under Federal case law, Federal law, policy & news, Payment Bonds, Subcontractors, Surety Law

N.C.’s Lien Law Study Committee Makes Progress, But Time Is Running Short

Monday MemoNorth Carolina’s House Committee on Mechanics’ Liens and Leasehold Improvements gathered for the third of four scheduled meetings last Friday, March 7.  Up for discussion were two legislative proposals: one that would strengthen liens on leaseholds, and one with the potential to weaken the “direct liability” or “wrongful payment” liens of subcontractors and suppliers.

Progress was made on both proposals, but with the Committee scheduled to meet for the last time and issue its recommendations on April 7, the clock is ticking on what might be accomplished during the legislative short session convening in May.

Here’s what you need to know about where things stand and what happens next:

Continue reading

Leave a comment

Filed under Lien Law, State law, policy & news, Subcontractors