Tag Archives: filing bond claims on time

Your Date of Last Furnishing of Labor Might Be Earlier Than You Think

Embed from Getty Images

Meeting lien and bond claim filing deadlines can sometimes feel like a race against the clock.  For claimants who provide on-site labor for a construction project, properly identifying the date such labor was last furnished is a critical component to winning that race.

Wednesday WisdomAn unpublished Fourth Circuit Court of Appeals decision illustrates the point.  In U.S. ex rel. Mavis Mechanical Services, Inc. v. Hanover Ins. Co., 182 F.3d 910 (4th Cir. 1999), a subcontractor on a federal construction project tried to establish compliance with the Miller Act’s one-year filing deadline by arguing it furnished labor on two occasions within a year of its lawsuit.  The first instance involved attendance at a coordination meeting; the second involved mobilization to the site to perform certain valve installation work it had yet to complete, but refusal by the sub to actually perform the work when the GC refused to make payment on alleged past due amounts.  On these facts, the Fourth Circuit upheld the district court’s determination that neither site visit qualified as “labor” for the purposes of the Miller Act’s one-year filing deadline.  That holding doomed the sub’s Miller Act claim to dismissal.

The moral of the story?

Continue reading

Leave a comment

Filed under Lien Law, Payment Bonds