COA: “No Damages For Delay” Clause Does Not Defeat Equitable Adjustment Clause

“Time is money.”  Sure, it’s an overused cliché.  But as construction industry participants know better than just about anyone else, there’s a whole lot of truth in those three simple words.  When projects run late, completion costs invariably rise, frequently resulting in the assertion of delay claims (and counterclaims.  And third-party claims.  And cross-claims … you get the picture).  “No damages for delay” clauses in construction contracts seek to manage loss exposure arising from delay by limiting a contractor’s remedy for delay to a time extension only.  A typical “no damages for delay” clause might read as follows:

The Owner shall not be liable to the Contractor and/or any Subcontractor for claims or damages of any nature caused by or arising out of delays.  The sole remedy against the Owner for delays shall be the allowance of additional time for completion of the Work, the amount of which shall be subject to the claims procedure set forth in the General Conditions.~ Werner Sabo, Legal Guide to AIA Documents, 2008 (5th ed.)

Such clauses aren’t always enforceable.  In fact, under North Carolina statutory law, “no damages for delay” provisions are unenforceable in prime contracts between public owners and general contractors.  See N.C. Gen. Stat. § 143-134.3.  But in all other cases where such clauses are enforceable, do they provide an impenetrable defense against increased costs arising from project delay?  Not necessarily. Continue reading

2 Comments

Filed under Delay Claims, Feature story, Material Cost Escalation, NC case law